Residents and businesses across Greater Masaka can look forward to fewer blackouts after the Uganda Electricity Distribution Company Limited (UEDCL) began a major upgrade of a critical power line that has long been a weak point in the region’s electricity network.
On 26 November 2026, UEDCL kicked off a Shs931 million refurbishment of the Masaka Central–Masaka West 33kV interconnector. The four-month project will improve supply reliability for more than 130,000 customers in Masaka City and the districts of Masaka, Kalungu, Bukomansimbi, Kalangala, Kyotera, Sembabule, and parts of Mpigi including Kayabwe and Buwama.
The 7.605-kilometre line has been a major source of frustration. UEDCL Territory Manager for Greater Masaka, Benjamin Busingye, said the ageing and overloaded interconnector accounts for roughly 90 per cent of medium-voltage interruptions in the area. “Out of every ten interruptions, about nine are associated with this line,” he noted at the start of the works. “Refurbishing it is therefore a major intervention towards improving the reliability of electricity supply for our customers.”
Demand in Greater Masaka has more than doubled in the past seven years, rising from about 15MVA to more than 30MVA as households, businesses and industries have grown. The existing 75mm² conductors were only designed to handle around 20MVA and could no longer cope.
Under the upgrade, crews will replace those conductors with larger 150mm² ones, lifting the line’s capacity to approximately 30MVA. They will also replace more than 70 deteriorated poles (using concrete poles in swampy sections for better durability), upgrade underground cables to larger 300mm² ones along a 190-metre stretch, and modernise current transformers that support the protection systems.
Senior Territory Engineer Eng. Bruce Kizito explained that the bigger conductors and upgraded cables will allow the entire interconnector to handle the higher demand that has built up in the region.
UEDCL is not stopping at the current refurbishment. The company is also pursuing a second interconnector between the same two substations. Once built, the parallel line will give operators an alternative route, so power can be switched if one line develops a fault or needs maintenance. That redundancy is expected to further reduce both the frequency and duration of outages.
Works on the current upgrade are scheduled for completion by the end of January 2027. UEDCL has urged the public to help protect the new and existing infrastructure by reporting vandalism or suspicious activity around power installations, noting that theft and damage continue to undermine reliability efforts.
The project forms part of UEDCL’s wider push to strengthen the distribution network, match rising demand, and deliver more dependable electricity to homes, shops, farms and industries across Greater Masaka.